Mink Ranch Road Rehabilitation

Update 7/18:

Milling of Mink Ranch Road is scheduled to begin on July 23rd-24th. Utility work should be completed between the 25th and the 27th. This schedule is contingent on other projects and weather permitting.

Update 7/10:

Stark Pavement is planning to begin work on Mink Ranch Road during the week of July 15th. The road will remain open to traffic during the milling and paving operation. When contractors are working on the sewer, the road will be completely shut down – this should be completed within one day.

We will update this post with more specific information as it becomes available.