OAK KNOLL ROAD REHABILITATION PROJECT UPDATE – MAY 14, 2026
VILLAGE OF ROCHESTER
OAK KNOLL ROAD REHABILITATION
PROJECT UPDATE – MAY 14, 2026
• May 18th – 22nd – Canadian National Railroad will be closing the crossing near the
west limits of Oak Knoll Rd. to replace the railroad crossing. No traffic will be able to
cross during this time frame.
• May 26th – 28th
- Payne & Dolan will pave the lower layer of asphalt on Oak Knoll Rd.
This will not include driveways. Driveways will be paved when the final layer of
asphalt is paved.
• Week of May 18th, KR will be onsite to continue to grade ditches and do more ditching
where needed.
• Concrete Curb on west side of project is being placed on 5/14, will require 7 days of
cure time prior to paving operations