🚧 ROAD PROJECT UPDATE – JUNE 4, 2026 🚧
Here's the latest progress on the Oak Knoll and Ridge Lane road improvement projects:
Oak Knoll
- Asphalt paving is complete
- Shouldering is expected to be finished by Monday
- Line striping is scheduled for the middle of next week
- Restoration and seeding will begin on June 10
Ridge Lane
- Chip sealing is complete
- Sweeping will be completed by the end of the week
- Fog sealing is planned for the coming weeks and will be completed one lane at a time
- Please note: Wet fog seal cannot be driven on, but it dries quickly
- Additional updates will be provided once the fog sealing date is finalized
Thank you for your patience as we continue making improvements to our community streets.