🚧 ROAD PROJECT UPDATE – JUNE 4, 2026 🚧

🚧 ROAD PROJECT UPDATE – JUNE 4, 2026 🚧

Here's the latest progress on the Oak Knoll and Ridge Lane road improvement projects:

Oak Knoll

  • Asphalt paving is complete
  • Shouldering is expected to be finished by Monday
  • Line striping is scheduled for the middle of next week
  • Restoration and seeding will begin on June 10

Ridge Lane

  • Chip sealing is complete
  • Sweeping will be completed by the end of the week
  • Fog sealing is planned for the coming weeks and will be completed one lane at a time
  • Please note: Wet fog seal cannot be driven on, but it dries quickly
  • Additional updates will be provided once the fog sealing date is finalized

Thank you for your patience as we continue making improvements to our community streets.